1. The plot
Everything starts with the planning status of the land. On an urban plot the municipal plan tells you how many square metres you can build, how high, how far from the boundaries and for what use. On rustic land a house is only possible in certain categories and above a minimum plot size. Check access, water, electricity and sewerage as well: bringing utilities to a plot can be expensive. See buying a plot in Mallorca.
2. The team
Spanish law requires an architect to design the house and direct the works, a technical architect (aparejador) to direct the execution, and a health and safety coordinator. You will also need a geotechnical study of the ground and a topographic survey. A project manager is optional but valuable if you are not on the island.
3. The project
The architect first prepares a preliminary design, then the basic project — enough to apply for the licence — and then the construction project, with structure, installations and details. The more complete the construction project, the more reliable the builder's price.
4. The licence
The basic project is submitted to the town hall with the application for the building licence. The licence fees and the construction tax are paid, the municipal technicians report and, when everything is in order, the licence is granted. Works cannot start before that.
5. The builder
With the construction project, several builders quote the same measurements. The contract should fix the price, the schedule, the payment by certified progress, the penalties for delay and the guarantees. Do not pay large amounts in advance.
6. The works
A typical sequence is earthworks and foundations, structure, roof, enclosures, installations, finishes and exterior works. The architect and the technical architect visit regularly, order tests and certify each stage.
7. The end of the works
When the house is finished the technicians sign the completion certificate. With it you obtain the first occupation licence and the certificate of occupancy, sign the declaration of new building before a notary, register it and contract utilities.
Frequently asked questions
How long does the whole process take?
As a guide, two to three years from the purchase of the plot to moving in: several months of design, a licence period that varies widely between municipalities and twelve to eighteen months of works.
Can I act as my own developer?
Yes. Self-development is common for a family home. You hire the technicians and the builder directly and take on the role of developer, with its responsibilities.
Is ten-year insurance compulsory?
Developers of housing must take out ten-year structural insurance. A self-developer building a single home for their own use may be exempt, but the insurance will be required if the house is sold within ten years, unless the buyer waives it.