Price
The contract can be for a closed price (a lump sum for the whole project) or by measurement (unit prices applied to the quantities actually built). In both cases the price must refer to a complete construction project and a detailed list of items; anything that is not described will become an extra.
Schedule and penalties
- Start date linked to the licence, and completion date.
- Intermediate milestones.
- A daily or weekly penalty for delay attributable to the builder.
- What counts as a justified delay — weather, changes ordered by the owner — and how it is documented.
Payments
Payments should follow the work: monthly certificates of work actually done, checked by the technical architect and the project manager. Avoid large advance payments. A retention on each certificate, returned at the end of the guarantee period, is customary and keeps the builder interested in repairing defects.
Changes
No change without a written order that states its price and its effect on the schedule, signed before it is built. This single clause prevents most disputes at the end of the works.
Insurance, guarantees and termination
- The builder's civil liability and construction all-risk insurance.
- Proof that the builder is up to date with tax and social security, and control of subcontracting.
- Legal guarantee periods for defects.
- Causes for termination and what happens to materials and work in progress.
- Jurisdiction and language of the contract.
A contract of this kind should be drafted or reviewed by a lawyer; we work with Castell.law.
Frequently asked questions
Is a contract in English valid?
A contract can be bilingual, but it should state which version prevails and it will normally be the Spanish one before a Spanish court.
Can the price be revised for increases in materials?
Only if the contract provides for it. In a closed-price contract the risk of price increases lies with the builder unless otherwise agreed.