Handover of the works, snagging and building defects in Spain

The last ten per cent of a building project takes more effort than it seems. A well-organised handover and knowing your guarantees save years of arguments.

The handover

The works are received in a signed handover record (acta de recepción). Before signing, the house is inspected room by room and a snagging list is drawn up with a deadline for each repair. The record can be signed with reservations; the guarantee periods start to run from the reception.

Documents you should receive

  • Completion certificate signed by the architect and the technical architect.
  • As-built plans and the building book, with instructions for use and maintenance.
  • Certificates and guarantees of installations and equipment.
  • The documents needed for the first occupation licence and the certificate of occupancy.

Guarantee periods

Spanish building law sets three periods of liability from the reception of the works:

  • One year for defects in finishes, for which the builder answers.
  • Three years for defects that affect habitability: damp, insulation, installations.
  • Ten years for structural damage that compromises the stability of the building.

Claims must be made within the time limits the law establishes once the damage appears, so defects should be notified in writing as soon as they are detected.

The retention

The amount retained from the builder's certificates is released when the guarantee period agreed in the contract ends and the defects have been repaired. It is the simplest way of making sure the builder comes back.

If the builder does not respond

Document the defect with photographs and a technical report, notify the builder formally and, if there is no answer, repair at the builder's expense using the retention or claim through the courts. Our project managers prepare the technical part and the lawyers of Castell.law the legal one.

Frequently asked questions

Can I move in before the handover?

It is better not to. Occupying the house can be interpreted as tacit acceptance of the works and complicates the snagging.

Do guarantees pass to a buyer if I sell?

Yes. The legal liability for building defects benefits successive owners during the periods established by law.

Contact

Tell us about your project

Describe the plot, the house or the idea and we will come back to you with a first assessment: what can be done, which permits it needs and how we would organise it.

  • First consultation free of charge and without obligation
  • A reply from an architect, not from a call centre
  • Projects in Mallorca, Ibiza, Menorca and Formentera